The Package 9 works include two pump houses, Malkampet reservoir, a tunnel and 27.50 km of canals. In all, 86,150 acres would be irrigated under the package once completed

By   |  Published: 3rd Jul 2020  9:37 pm
IT and Industries Minister KT Rama Rao at a review meeting with officials on the Kaleshwaram project, at Pragathi Bhavan in Hyderabad on Friday.

Hyderabad: Minister for IT and Industries KT Rama Rao has directed Kaleshwaram Lift Irrigation Scheme (KLIS) engineers to complete Package-9 works before October and to prepare an action plan to fill 666 ponds.

Speaking at a review meeting here on Friday at Pragathi Bhavan, the Minister asked Kaleshwaram ENC Nalla Venkateswarlu, Government Lift Irrigation Adviser Penta Reddy and Superintending Engineer Sudhakar Reddy to asses and also speed up works on the 12.035-km tunnel, pump house and surge pool. He asked them to review progress at the ground level and also with contractors.

“We are hopeful of filling Upper Manair with water from Mid Manair by the October-end. Meanwhile, we must complete the Package-9 works such as construction of main canal, and land acquisition and construction of distributary canals,” he said, adding that the package would bring additional 30,000 acres of new ayacut. The Package 9 works include two pump houses, Malkampet reservoir, a tunnel and 27.50 km of canals. In all, 86,150 acres would be irrigated under the package once completed.

Irrigation Principal Secretary Rajat Kumar, Sircilla District Collector Krishna Bhaskar and Executive Engineer Srinivas Reddy were also present at the meeting.

MLAs seek KTR’s support for coach factory

Hyderabad: The elected representatives of erstwhile Warangal district on Friday called on Minister KT Rama Rao seeking his support for the establishment of much-awaited Railway Coach Factory at Kazipet.

Government Whip Dasyam Vinay Bhaskar, MLC Pochampally Srinivas Reddy and Wardannapet MLA Aroori Ramesh submitted a representation to the Minister at Pragathi Bhavan here on Friday.

They informed the Minister that despite numerous agitations and requests, the factory remained a distant dream for people of the region. They said that necessary land had been identified, but the Centre was not responding to requests from the State in this regard. They hoped that following the intervention of Rama Rao, the Centre would respond positively and initiate necessary steps to establish the factory which would eventually provide employment to the local youth and get national-level recognition to the area.


Now you can get handpicked stories from Telangana Today on Telegram everyday. Click the link to subscribe.

Click to follow Telangana Today Facebook page and Twitter .