GHMC speeds up H-CITI works around KBR National Park
GHMC Commissioner R.V. Karnan has directed TGSPDCL to expedite utility shifting for the H-CITI elevated corridor around KBR National Park. Officials reviewed the 4.3-km project and ordered faster junction upgrades, foundation investigations, excavation and steel fabrication works
Updated On - 24 October 2026, 08:41 PM
Hyderabad: The GHMC has directed the Telangana State Southern Power Distribution Company Limited (TGSPDCL) to expedite the shifting of obstructive electrical networks and utilities around KBR National Park to speed up works being undertaken under the H-CITI project.
GHMC Commissioner R.V. Karnan and senior officials reviewed the 4.3-km elevated corridor project on Saturday. The project aims to ensure signal-free traffic movement from Jubilee Hills Checkpost to NFCL Junction.
Officials directed that junction improvement works at the KBR Park main entrance, Agrasen Junction and Jubilee Hills Checkpost be fast-tracked to streamline one-way traffic around KBR Park.
The Commissioner also called for immediate coordination with TGSPDCL to relocate utilities around KBR Park and expedite foundation design investigations between Mugdha Junction and NFCL Junction.
Foundation excavation and off-site steel fabrication works between Jubilee Hills Checkpost and Mugdha Junction were also ordered to be expedited.