RINL production hit due to power issues
Visakhapatnam: Production in RINL-Visakhapatnam steel plant was interrupted on Tuesday due to a snag in the thermal power plant (TPP)-1. There was a power trip in the operating panel-9 of the TPP1 which saw charring of the cables leading to backfire in the boilers. As many as five boilers stopped functioning resulting in power production. […]
Published Date - 1 December 2020, 06:43 PM
Visakhapatnam: Production in RINL-Visakhapatnam steel plant was interrupted on Tuesday due to a snag in the thermal power plant (TPP)-1.
There was a power trip in the operating panel-9 of the TPP1 which saw charring of the cables leading to backfire in the boilers. As many as five boilers stopped functioning resulting in power production.
The RINL officials were busy with damage control exercises on the day.
Now you can get handpicked stories from Telangana Today on Telegram everyday. Click the link to subscribe.
Click to follow Telangana Today Facebook page and Twitter .