Govt issues show-cause notices to Nagarjuna Sagar engineers after KTR questions inaction on AP diversion
The Telangana government has issued show-cause notices to Nagarjuna Sagar project engineers for failing to alert it about Andhra Pradesh's ongoing water diversion project. The move has sparked questions over the government's delayed response, particularly after BRS leader KT Rama Rao highlighted the issue and challenged the administration's claims of acting swiftly.
Updated On - 19 November 2026, 01:55 PM
Hyderabad: Hours after Irrigation Minister N Uttam Kumar Reddy claimed to be aware of the Andhra Pradesh’s water diversion project from Nagarjuna Sagar and said he had written to the Krishna River Management Board (KRMB) in this regard, the State government issued show-cause notices to the project’s senior authorities over their failure to alert it about the project.
The notices were issued on Wednesday to the project’s Superintending Engineer and Executive Engineers, asking them to explain within a week why action should not be taken against them for failing to alert the government about Andhra Pradesh’s project.
The State government’s decision to issue show-cause notices has exposed the delay in its response to the issue, which came under sharp political scrutiny after BRS working president KT Rama Rao questioned the government’s inaction. The move also raises questions over the government’s attempt to shift responsibility to field-level officials for an issue that concerns the State’s water security.
Andhra Pradesh began work in March this year on a Rs 1,200-crore project involving three intake wells on the right side of Nagarjuna Sagar and 200 tanks to draw 1.86 TMC of water for drinking needs in Palnadu district. The works have reportedly been under way for eight months.
The government is said to be unhappy that the Nagarjuna Sagar engineers failed to flag the project during this period. However, the action against them comes after Rama Rao questioned how the proposed diversion and ongoing works had escaped the attention of the Chief Minister, the Irrigation Minister and the administration.
The timing is significant. On Wednesday, Irrigation Minister N Uttam Kumar Reddy claimed that the government was swift in responding to Andhra Pradesh’s plans and had already taken up the matter with the Krishna River Management Board (KRMB) and the Centre. Yet, the government’s letter to the KRMB seeking intervention was sent only less than a week ago, despite the project works having begun in March.
The show-cause notices, rather than establishing the government’s prompt response, have only exposed the gap between the Minister’s claims and the timeline of official action. Holding engineers accountable for not reporting the project does little to explain why the government machinery failed to detect and act against the works for months.