Irrigation Minister Uttam Kumar Reddy informed that a detailed presentation on the Banakacherla project would be held at Praja Bhavan on June 30 at 3 PM.
-
Former BRO Director-General Lt. Gen. (Retd.) Harpal Singh will join the mission as an honorary advisor, bringing decades of tunneling experience.
-
Telangana is set to resume work on the SLBC tunnel with help from Indian Army and BRO experts. High-tech surveys using Danish equipment and LiDAR will begin July 12, following a fatal collapse in February that halted the project
-
The SLBC tunnel collapse killing eight workers, has spotlighted Jaiprakash Associates’ failure to address geological risks flagged in prior surveys. As rescue efforts end, accountability and safety lapses raise concerns about project management
-
He posted on X, "With a capable leader and a fully functional government, humans could have been brought back from Mars within three months. But because it’s the Congress, they haven’t even managed to recover the bodies from the tunnel."
-
Operations at the tunnel have been halted, leaving the mission unfinished and the fate of six missing workers uncertain. Approximately 120 personnel from Singareni Collieries Company Limited (SCCL) and the State Disaster Response Force (SDRA) are still engaged in the final stages of the operations.
-
Political involvement proved to be a distraction; Ministers’ focus on defending lapses at the worksite added to the chaos rather than resolving it
-
Despite the tireless work of 12 specialised agencies, the mission is wrapping up without locating the six missing workers who were trapped after the tunnel roof collapsed on February 22
-
The operations were scaled up by engaging as many as four mini-excavators.
-
Harish Rao called for a thorough investigation into the incident and the reported lapses in the rescue operations. Holding the Revanth Reddy-led government responsible, he said eight workers remain trapped inside the tunnel due to the administration’s negligence. “This government's carelessness has thrown the lives of eight innocent individuals into uncertainty and left their families in deep anguish,” he stated.
-
Although the original target was to finish the task by April 10, progress has been hindered by slushy conditions due to rising water seepage at the accident site. However, officials remain hopeful that the tunnel will be cleared up to the cave-in point by April 15, as long as operations continue smoothly.
-
Sensors installed to continuously monitor air quality; adequate airflow procedures being implemented to support rescue efforts
-
During a visit to the accident site, Srinivas Reddy highlighted the swift progress of rescue efforts. The clearing of the 105-110 tunnel stretch still left filled with debris would resolve the issue.
-
In a fresh attempt to assess the progress of the rescue operations, SLBC Tunnel Special Officer Siva Shankar Lotheti reviewed the situation at the tunnel office on Tuesday
-
The conveyor belt was being restored from 13,630 metres to 16,730 metres inside the tunnel. Suggestions from experts were being taken to effectively take up the rescue operations.
-
This location was found after the removal of layers of debris around the area where the locomotive train got buried under the collapsed roof of the tunnel.
-
The five pumping stations equipped with 150 HP capacity each were pumping out over 55,000 gallons of water per hour into the Krishna River
-
Deceased identified as Manoj Kumar, engineer from Bangar Mau in Uttar Pradesh; Rs 25 lakh ex-gratia to be provided to his family
-
Revanth Reddy wants Telangana administration to obtain necessary clearances from the Centre to continue the search and salvage operations
-
Rescuers proceeding with extreme caution as the final 40-metre accident stretch is a ‘prohibited zone’